The Norton Knatchbull School needed multiple science labs fitted out to a high standard but faced supplier challenges mid-project.
The Norton Knatchbull School needed six new science labs to be fitted out with high-quality furniture and equipment. The project was planned in multiple phases, but due to external supplier issues, the school faced challenges in ensuring consistency in quality and timely delivery across all labs. Brookhouse was responsible for delivering the first two labs to the highest standards, setting the benchmark for future installations.

Partial project handover to another supplier
Maintaining quality despite supplier transition

Managing client expectations through unforeseen changes


Science Lab Fit-Out & Furniture Installation

Science Lab Fit-Out & Furniture Installation

Science Lab Fit-Out & Furniture Installation

Science Lab Fit-Out & Furniture Installation

Science Lab Fit-Out & Furniture Installation

Science Lab Fit-Out & Furniture Installation

Education
How Brookhouse helped The Norton Knatchbull School enable success for their science labs.
We completed the fit-out of two labs and had prepared furniture for additional spaces before project disruptions. Though the remaining work had to be completed by another supplier, the school noted that our quality was superior, reinforcing our reputation for excellence.